Samtredia-Grigoleti Road - Lot I |
Length of the section to be constructed – 11.5 km
Donor - European Investment Bank (EIB) and State Budget GOG
Upgrading of 57 km Samtredia-Grigoleti road will be implemented in 4 lots. Tender procedures for LOT I (11.5 km long section) were completed in 2013. Construction works will enter into active phase in 2014. Four-lane asphalt-concrete road with a new alignment would be constructed at respective section.
Artificial structures:
Interchange – 2
Bridge – 2
Overpass – 2
Viaduct with length 503.36m – 1
Construction works were carried out by the company: "JEU Group".
Samtredia-Grigoleti Road - Lot II |
Length of the section to be constructed – 18.5 km.
Were constructed:
- 9 bridges
- 3 interchanges
- 76 rectangle pipes
Construction works were carried out by the company: “Sinohydro”.
Samtredia-Grigoleti Road - Lot III |
Length of the section to be constructed – 12 km.
Donor – European Investment Bank (EIB)
The construction project of the third lot of Samtredia-Grigoleti envisages construction of four-lane asphalt concrete road, 9 bridge crossings, 2 interchanges and 65 rectangular pipes (overpasses, field and cattle passes).
The third section of Samtredia-Grigoleti road will pass through the city of Lanchkhuti and villages of the Lanchkhuti Municipality.
|
Samtredia-Grigoleti Road - Lot IV |
Length of the section to be constructed – 9.5 km.
Donor – European Investment bank (EIB)
The project envisages the construction of the four-lane asphalt concrete road with the new direction on a 9.5 km section of road.
Were constructed:
2 viaducts
- 1 interchange
- 42 reinforced concrete underpasses and culverts
Construction works were carried out by the company: „China Railway 23rd”